SC invokes Article 142 to acquit POCSO convict after victim marries him
However, the apex court clarified that the relief was being granted in the peculiar facts and circumstances of the case and would not serve as a precedent.
(Photo: SNS)
The Supreme Court (SC) on Monday asked real estate developer Unitech to deposit 14 per cent interest on Rs.16.55 crore for delay in delivery of flats to 39 buyers.
“SC asks Unitech to deposit 14 per cent interest on the principal amount of Rs.16.55 crore deposited by 39 flat buyers,” reports stated, adding, “The interest on the principal amount will be calculated from January 1, 2010”.
Advertisement
Meanwhile, setting the time limit for deposit of interest amount, the apex “court has asked Unitech to deposit interest amount in eight weeks," sources said.
Advertisement
The SC, in October last year, had asked the company to refund the deposited amount to 39 homebuyers of its Gurgaon project for delay in delivery of flats.