Logo

Logo

Lapses in Rly track safety measures exposed

The Railways needs to strengthen track safety measures as an audit has revealed several lapses in maintenance plans, inspection schedules…

Lapses in Rly track safety measures exposed

Representational Image (Photo: Subrata Dutta/SNS)

The Railways needs to strengthen track safety measures as an audit has revealed several lapses in maintenance plans, inspection schedules and use of high-end machines procured to detect track defects, according to a CAG report tabled in Parliament on Tuesday.

The Comptroller and Auditor General of India (CAG) report said that during 2014-2015 to 2016-2017, 16 accidents or derailments took place due to deficient track maintenance in five zonal railways (South Western Railway, North Central Railway zone (NCR), East Central Railway zone (ECR), South Eastern Railway zone (SER) and Southern Railway) it audited.

It said that 294 permanent speed restrictions (PSR) were imposed on select sections because of track vulnerability. The audit covered the period from 1 April 2016 to 31 March 2017, focusing on maintenance of tracks on 29 sections of high-density network routes (HDN) and eight sections of non-HDN routes.

Advertisement

“Audit of 37 selected sections of the Indian Railways showed that track maintenance activities needed to be strengthened and undertaken following the laid down instructions and guidelines…Inspections were not being done as per laid down frequency by railway officials,” the report said.

The report said while in North Central Railway zone (NCR) and East Central Railway zone (ECR), maintenance plans were not prepared, South Eastern Railway zone (SER) was rectifying deficiencies on inspection and not as a preventive measure as is the norm.

It also said that patrol men were not equipped with any communication equipment to report any failure, fracture or damage immediately from the sections where they have been observed. “Audit noticed shortfalls and deficiencies in inspections carried out at different levels…testing of rails using Ultrasonic Flaw Detection (USFD) machines was not carried out as per the prescribed norms,” the report stated.

The report also said deep screening of ballast which is required to restore the resilience and elasticity of the ballast bed and for improving running quality of track had significant backlog and in some sections it was overdue for one to 22 years.

The audit noticed 274 cases of rail fractures and 465 cases of weld fractures during 2015-2016 and 2016-2017 in the selected zones. During this time seven accidents occurred due to rail fractures, it said.

The report also stated that that there was shortage of staff in different safety categories responsible for track maintenance ranging from nine to 22 per cent in different railway zones.

“The situation was made worse by diverting available track maintainers to works other than track maintenance… more track maintainers have been posted to bigger cities than remote locations though the requirements for the whole section may be uniform,” the report said, adding that there was a shortage of about 50 per cent blocks against the block demanded by the engineering department for maintenance work.

The report said zonal railways impose speed restrictions on various sections due to poor track structure.“Each speed restriction has a cost attached to it and prolonged imposition would also have a financial impact in addition to the operational impact. It is therefore necessary to ensure completion of works within a set time frame so that speed restrictions are removed at the earliest,” CAG said.

Advertisement